Lets you specify a date for the Time Now Line in the Task Timeline, Resource Timeline, and Resource Histogram. The line is displayed at the current date unless you change it with this command.
The Time Now Line appears as a bold vertical line in the chart. If you don’t want the line to appear, simply specify a date that is outside the time span of your project.
-- part contents for background part 7
----- text -----
Lets you change the time intervals used in the Task Timeline, Resource Timeline, Cash Flow Table, and Resource Histogram. This command does not affect the duration scale.
You can also set a start date for the time intervals with this command. If you do not set a date, MacProject II uses the first working day of the project calendar.